Saturday, 28 June 2025

Future of Indian Coal Industry in the Era of Net Zero

 Introduction

United Nations Framework Convention on Climate Change (UNFCCC) in its 26th Conference of Parties (COP 26), held at Glasgow, United Kingdom desired different countries to declare their resolve for Net Zero timelines. While USA fixed 2050 for meeting this requirement, China promised it to be by 2060 and India declared it to be achieved by 2070. Before we proceed further on the subject, it would be prudent to understand what is meant by “Net Zero” and what have been the pledges of India, as promised by our honorable Prime Minister. In this article an attempt has been made to assess the impacts of the pledges on the coal industry of India.

Understanding Net Zero

Net Zero Emission or Net Zero means not adding to the amount of greenhouse gases in the atmosphere. Net-zero emissions will be achieved when all Green House Gas (GHG) emissions released by human activities are counterbalanced by removing GHGs from the atmosphere in a process known as carbon removal. Achieving it means reducing emissions as much as possible, as well as balancing out any that remain by removing an equivalent amount.

Greenhouse gases like carbon dioxide (CO2) are released when we burn combustible material, such as oil, gas, coal, and biomass, for our homes, factories, and transport. Methane is produced through farming and landfill. These gases cause global warming by trapping the sun's energy.

The idea of “Net Zero” was promoted in a 2018 special report from the Intergovernmental Panel on Climate Change (IPCC) which demanded that countries bring greenhouse gas emissions to “net-zero” by 2050 to keep global warming to within 1.5°C of pre-industrial levels. The target for achieving this was kept as year 2050, while limiting that to 2.0oC level was kept as year 2100.

Importantly, the time frame for reaching net-zero emissions is different for CO2 alone versus for CO2 plus other greenhouse gases like methane, nitrous oxide, and fluorinated gases. For non-CO2 emissions, the net zero date is later, because models assume that some of these emissions — such as methane from agricultural sources — are more difficult to phase out.

All countries in the G7 - representing the world's largest advanced economies believe that the human-caused emissions from fossil-fueled vehicles and factories, should be reduced as close to zero as possible. Any remaining GHGs should then be balanced with an equivalent amount of carbon removal, which can happen through things like restoring forests or using direct air capture and storage (DACS) technology.

It is also necessary that the transition from the current approach of energy generation toward net zero is done in a just manner, especially for workers tied to high-carbon industries and also the population dependent on such activities for their livelihood. In fact, the costs and benefits of transitioning to a net-zero emissions economy must be distributed equitably.

Global action for setting net-zero targets is growing fast, with major economies like China, United States, India, and the European Union making all efforts to meet such commitments. Bhutan was the first country to set a net-zero target in 2015. Now over 90 countries, representing nearly 80% of global emissions, are covered by a net-zero target.

It is pleasant to note that most of the technologies needed to reach net zero targets are already available and becoming increasingly cost-competitive with high-carbon alternatives. Solar and wind now provide the cheapest power available for most of the world. Markets are responding to these opportunities and to the risks of a high-carbon economy, and they are shifting accordingly.

CO2 Emission in India by Fuel Type

Even though coal accounts for only 55% of the primary energy in the country, it is responsible for more than 2/3rd of the CO2 emitted to the atmosphere. The chart below shows how the CO2 emission from coal has increased over the last 30 years.

 

 Other includes flaring, cement production and other industrial emissions

Source: Global Carbon Project 2021

 India’s Carbon Emission compared to other Countries

In the year 2020, though India, as a country, ranked third in global carbon emission (nearly 2.6 Gt of CO2), it had contributed only one fourth that of China (10.7 Gt of CO2) and nearly half that of USA (nearly 4.8 Gt of CO2). All other countries produced much lower CO2.

India’s Carbon intensity of Energy Production – Highest in the world.

With the increasing use of inferior grade coal for power generation in India, the amount of carbon dioxide (CO2) produced for one unit of power (kWh) production in India is the highest now, at the level of around 0.275 kg/kWh, overtaking China, which had been the topper in this category, so far. Most of the European Union and North American countries produce CO2 in the range of 0.11 kg – 0.20 kg per kWh. The following graph shows the status of different countries:

 

India’s Commitment at COP26

Hon’ble Prime Minister of India during his speech at COP 26 made the following pledges on India’s decarbonisation roadmap:

 

1.     Increase non-fossil energy capacity to 500 GW (gigawatts) by 2030.

2.     Meet 50 percent of energy requirements from renewable energy (RE) by 2030.

3.     Reduce the total projected carbon emissions by 1 billion tonnes (BT) by 2030.

4.     Reduce the carbon intensity of the economy by less than 45 percent.

5.     Achieve net zero carbon by 2070.

Impact of COP 26 Pledges on Indian Coal Sector

Of the above 5 pledges, the first two relate to building up the capacity of renewable energy to 500GW by 2030, being 50% of India’s total energy requirement by this time. This indicates that the total installed capacity of fossil fuels-based power generation would be around 500GW by 2030 meaning thereby that coal being the major contributor of energy intensity amongst the fossil fuels, its share in quantum as energy provider will increase at least up to 2030, but in percentage terms it is bound to reduce from the current level of 55% in the total primary energy basket. This shows that power generation from coal is projected to increase in near future terms.

The major concern for the coal sector lies in pledge No. 3, which requires the country to reduce the total projected carbon emission by 1 BT by 2030. This is a radical pledge as it promises an absolute reduction in carbon dioxide (CO2) emissions by 2030.  While the projected CO2 emission by 2030 is not known, its reduction by 1 BT would mean reduction of fossil fuel usage by about 590 MT coal equivalent from the projected level for 2030. This is a serious threat on usage of coal as energy provider.

The last pledge of achieving net zero status by 2070 gives us enough time to adhere to it. It also provides the scope of emitting or generating CO2 and planning for sequestering it through the trees and artificial processes to keep it at net zero level.

 

Past trend of coal consumption in the country

 

The trend of total annual coal consumption in the country, including domestic coal, lignite, the imported coal, coke and other products is shown in the following chart. It shows that there has not been substantial increase in the coal usage in the country in the past ten years. Total consumptions in the last 5 years have been hovering between 950 MT to 1100 MT. Years 2019-20 and 2020-21 saw a slight declining trend while the past two years have seen increased usage of the solid fossil fuel in the country.

 

Source: Data taken from Coal Statistics 2022-23

 

All India Power Generation Capacity and Energy Generated in June 2023

 

India’s target for capacity creation of Renewable Energy was 175 GW by December 2022, which was missed. However, by the end of June 2023 it has surpassed that target by increasing the capacity to 176.49 GW, out of the total power installed capacity of 421.90 GW, which is 41.83% of the total. Compared to this the share of energy generation has been only 23.83% from the renewables. Installed capacity of renewable based (non-fossil fuel based) generators must be increased to 500 GW by the end of 2030 as per the pledge, which seems to be catching up.

 

Coal based installed capacity of power generators by the end of June 2023 has been 212.52 GW (50.27% of total of 421.90 GW). This along with the gas and diesel generators (thermal) contributed 72.82% of the total energy generated in June 2023. This indicates that even though the installed capacity of renewables-based energy generators will increase, the load on energy generation will continue to be on the fossil fuel-based generators.


                                                                                 Source – CEA                                                                                               


Growth of RE installed Capacity in last 6 Years

 

In the past 6 years, there has been substantial growth in the installed capacity of renewables based generating capacity creation from nearly 50 GW in January 2017 to 176 GW in June 2023, largely due to increase in solar power from 9 GW to 70.10 GW and wind from 28.7 GW to 43.77 GW. This is also an indicator that the target of 2030 of 500 GW can be reached safely by enhanced drive in solar and wind power.

 


Source - CEA

 

 Future Projection for Coal Based Energy Plan for India

 

The Draft National Energy Policy of 2017, published by NITI Ayog, mentions that the large power requirement and solid fuel demand in process industries brings to fore the need for efficient coal exploitation, investment in related infrastructure, and a forward-looking regime. The large planned new coal based thermal capacity is likely to put pressure on coal resources. It further mentions that Coal based power generation capacity is likely to go up to more than 330-441 GW by 2040. This is likely to translate into a coal demand of 1.1-1.4 billion tonnes annually. As per this assessment, at high rates of coal demand, domestic coal supplies may plateau by the year 2035.

 


Source: Draft National Energy Policy, 2017

The overall coal demand for the country was estimated to be at 1300 – 1900 MT by 2030, as per the Coal Vision 2030 document of Ministry of Coal.

 

The National Electricity Policy, 2021 also highlights the role of coal in electricity generation. On thermal generation it clarifies that while India is committed to add more capacity through non-fossil sources of generation, coal-based generation capacity may still be required to be added in the country, as it continues to be the cheapest source of generation, though compliance to stricter environmental norms remain a challenge, particularly in older stations. The Policy stresses that all future coal-based plants should only be of Super Critical/Ultra-Super Critical technology or other more efficient technology.

 

National Framework for Promoting Energy Storage for Renewable Energy

India's energy mix is set to undergo a transition from fossil fuel sources to non-fossil fuel-based sources dominated by Renewable Energy (RE) in the future.  However, the incorporation of a significant amount of variable and intermittent RE into the energy mix poses a challenge for maintaining grid stability and uninterrupted power supply. Power generation from the conventional energy sources as coal, hydro (with storage), nuclear can be controlled and can meet any fluctuation in the power demand in no time. However, the same is not the case with Renewable Energy (RE) sources as these are to be used instantly, and in case they are not utilised they will be lost forever.

Energy Storage Systems (ESS) can be used for storing energy available from RE sources to be used at other times of the day. Storage of energy will help in bringing down the variability of generation in RE sources, improving grid stability, enabling energy/ peak shifting, providing ancillary support services, and enabling larger renewable energy integration.

A National Framework on Energy Storage System (ESS) has been issued by the Government of India in August 2023 to encourage the adoption of Energy Storage for ensuring an environmentally sustainable and financially viable power sector.

Estimation of Energy Storage Requirement and Capital Required

As per National Electricity Policy (NEP), 2023 the energy storage capacity requirement is projected to be 16.13 GW [(7.45 GW Pumped Storage System (PSP) and 8.68 GW Battery Energy Storage System (BESS)] in year 2026-27, with a storage capacity of 82.32 GWh (47.6 GWh from PSP and 34.72 GWh from BESS).

The energy storage capacity required for 2029-30 is likely to be 60.63 GW (18.98 GW PSP and 41.65 GW BESS) with storage of 336.4 GWh (128.15 GWh from PSP and 208.25 GWh from BESS).

By the year 2031-32, this requirement is expected to increase to 73.93 GW (26.69 GW PSP and 47.24 GW BESS) with a storage capacity of 411.4 GWh (175.18 GWh from PSP and 236.22 GWh from BESS).

CEA has projected that by the year 2047, the requirement of energy storage is expected to increase to 320 GW (90GW PSP and 230 GW BESS) with a storage capacity of 2,380 GWh (540 GWh from PSP and 1,840 GWh from BESS) due to the addition of a larger amount of renewable energy considering the net zero emissions targets set for 2070.

To develop this storage capacity during 2022-27 the estimated fund requirement for PSP and BESS would be Rs. 54,203 Cr. and Rs. 56,647 Cr. Respectively, totaling Rs. 110850 Cr. Further, for the period 2027-2032 estimated fund requirement for PSP and BESS would be Rs. 75,240 Cr. and Rs. 2,92,637 Cr. Respectively, totaling Rs. 367877 Cr.

Actions Required for Continuing Usage of Coal in Future

Several actions are required for continuing usage of coal in the future. Coal has to compete with other sources of energy generation both environmentally and economically. Cost of power generation from renewables has been decreasing over the years and has come to a level much lower compared to that from fossil fuel. The daunting task for coal is the cost of carbon removal. Entire chain of coal sector players, ie, producer, transporter and user have to work together to make coal-based energy cost competitive with renewables, including the cost of carbon removal, that is carbon capture and storage.

Carbon capture and storage Initiatives in India

The greenhouse gas emission footprint of coal-fired power generation could be reduced by carbon capture, utilisation, and storage (CCUS). India has created a programme for CCS and is interested in promoting it through Mission Innovation. Several oil and gas companies, including ONGC, are investigating the potential for CO2-based enhanced oil recovery and NTPC is interested in CCS.

R&D in CCS is being pursued by CSIR laboratories and academic institutions under the programme initiated by the Department of Science and Technology. As part of Mission Innovation, initiation has been made for funding opportunity in the Carbon Capture Innovation Challenge for joint R&D in the field of CO2 capture, separation, storage, and CO2 value-added products to be taken up jointly by Department of Biotechnology and Department of Science and Technology with member countries of Mission Innovation. Large areas of our subcontinent may not be suitable for onshore CO2 storage due to high seismic activity and population density, and any CO2 storage activity would need to protect subsurface aquifers, which are vital source of ground water for drinking and agriculture.

Greening of India

One of the actions identified in the country’s National Determined Contribution (NDC) under the Paris Agreement sets out plans to create an additional carbon sink of 2.5-3 billion tonnes of CO2 equivalent through additional forest and tree cover. NASA Earth Observatory also indicates that India is greening. Although, there have been replanting initiatives in the western parts, the north-eastern region has lost forest cover in recent times. With an aim to plant enough trees by 2030, it may be possible to absorb additional 2.5-3.0 billion tonnes of CO2 annually from the atmosphere.

 


Source: NASA Earth Observatory

 

Conclusions

India's energy mix is set to undergo a transition from fossil fuel sources to non-fossil fuel-based sources dominated by Renewable Energy (RE) in the future.  Energy Storage Systems (ESS) can be used for storing energy available from RE sources to be used at other times of the day, for which massive investment is required. Investments in carbon removal techniques are also necessary to keep continued usage of coal. The different pathways assessed by the IPCC to achieve 1.50C by 2050 rely on carbon removal to some extent. Though, futuristic energy demand increase warrants huge investments in both sectors, ie, fossil fuel based and RE based energy, the ultimate choice will hinge upon the most economic and dependable supply system. Just transition is another issue that will require to be addressed, as in India, currently most of the economic activities are dependent on coal and other fossil fuels.

Different estimates show different amount of coal requirement for the future. World pressure for making all countries carbon neutral between 2050 and 2070, puts a huge challenge on coal and other fossil fuel usage to continue for long. While in the near future terms the requirement of coal may increase by, say up to 2040, in the longer terms it all depends on the progress made in carbon capture, storage and its utilization with its cost competitiveness with renewable based energy generation and the extent of greening the country by massive plantation.

Friday, 27 June 2025

Underground Coal Mine Production in India – Present Status and the Way Forward

 


ABSTRACT

 

Production from underground mines in India has been declining since eighties. The decline has been consistent from the level of 77.10 Mt in 1981-21 to 34.31 Mt in 2023-24, while the percentage share of UG production has reduced from 75% in 1971-72 to 3.44% in 2023-24. All stakeholders feel concerned about this decline and there is a need to reverse this trend and boost underground production. The inventory of Indian coal resource also suggests that the share of UG production needs to be increased for sustainability of domestic coal production in future. Various underground mining technologies have been tried in Indian mines in the past, but these have not yielded desired reduction in cost of production compared to opencast mining and many of them have failed. As such, these could not be replicated in other mines. Mass production technology with Continuous Miner has taken late entry in Indian mines. Also, there is ample scope for introduction of Highwall mining in many mines. Coal India Ltd. has prepared a vision document for boosting underground production to around 100 Mt by 2027-28, based on applicability of various modern suitable technologies in different mines. Implementation of this vision with rigorous monitoring is the need of time. This paper analyses various factors leading to decline in underground production and suggests the way forward for reversal of this trend.

 

1.             Underground coal mining in India – historical perspective

 

History of coal mining in India indicates that it was predominant by underground mining till the year of Independence. Some opencast mines were opened after formation of National Coal Development Corporation (NCDC) in the year 1956. Yet Underground Mining was the leader in coal production till the years of nationalization of coal industry (1971-73). The underground coal production in the FY 1973-74 was 58.37 Mt out of the total of 78.17 Mt, amounting to nearly 75% (1, 1984).

 

With completion of nationalization of coal mines, the underground mine production also grew up along with that of opencast mines and rose to the level of 75.53 Mt out of the total of 138.28 Mt (1, 1984), reducing its share to around 55%. Underground mine production started declining thereafter, while the production from opencast mines grew fast. By FY 2004-05 the UG production declined in quantity to 62.35 Mt (16.30% of the total) against the total of 382.61 Mt (2, 2014).

 

The declining trend continued year after year and in the next 19 years, that is by 2023-24 the coal production from UG mines in India reduced to 34.331 Mt (3.44% of the total) against the total of 997.826 Mt (3, 2024). This downfall in UG production is not only from CIL mines, the major producer of coal but also from the SCCL mines, which had been so far considered as substantial contributor to UG production. In the last two decades CIL’s UG production has declined from 47.041 Mt to 26.021 Mt (44.7%) while SCCL’s UG production has declined from 12.974 Mt to 5.931 Mt (54.3%) (2, 2014 & 3, 2024). The trend of Indian coal production since nationalization is shown in Fig. 1 (constructed from data in 1,1984, 2,2014 and 3,2024).

 


Figure-1


It may be worth mentioning here that alarmed by the steep decline in UG coal Production, Ministry Coal in 2007 asked Coal India to prepare a plan for boosting underground coal production and set up a target for increasing it to 75 Mt per annum by 2011-12. A nice document was prepared which was also monitored for some years, but unfortunately UG production in CIL further fell to 38.39 Mt in 2011-12 from the level of 43.322 Mt in 2006-07.

 

All the foregoing indicates that despite best of promises from the coal producers and the Government there exists a lack of thrust on the part of both to even arrest the decline, what to talk of increasing the level. It is for sure that the country could not have depended on UG production only for meeting the requirement of coal for growing demand of energy. Advent of advances in opencast mining came as a rescue for boosting production from opencast mines and thereby meeting the country’s coal requirement. However, it is also equally necessary to keep the underground mining alive and agile so that when opencast mining becomes unviable due to increasing depth, alternative method of coal production is also available in the country to replenish the shortfall.

 

There are valid reasons for decline in underground coal production. The author, with his vast experience in coal sector, has tried to analyse the reasons for the downfall and suggests some way forward to reverse the trend.

 

2.          UG coal production should be given a priority for reversal - reserves and resources criteria

 

Total coal inventory of India is assessed at 389.421 Bt as on 1st April 2024 (3, 2024). Depth-wise break-up of this resource is shown in Table-1.


Table-1

Depth-wise coal resource in India

(Resource in billion tonne)

Depth Range

Proved Reserve

Indicated Resource

Inferred Resource

Total

0-300m

140.921

57.845

7.512

206.277

300-600m

46.557

67.222

13.855

127.635

600-1200m

9.500

23.495

7.101

40.096

0-600m

15.229

0.154

0.029

15.413

Total

212.207

148.716

28.497

389.421


Considering about 50% of the resource in the depth range of 0-600m to be available in 0-300m, the total resource in the depth range of 0-300m works out to 213.983 Bt, accounting to 55% of the total. This means that 45% of the total resource lies in the depths exceeding 300m, which is currently considered as the maximum depth limit for economic and technically feasible opencast mining. Further, all the resources within 300m depth of occurrence are not mineable by opencast due to their availability in low thickness seam with high strip ratios. Also, the resources shown in the depth range of 0-300m have been extensively mined out over the years, which are not accounted for in the resource estimates. All these facts indicate that the resources that cannot be mined by opencast may be much more than the estimates above.

 

Current high production rate from OC mining and huge imbalance in production from the two technologies are likely to lead to fast depletion of mineable resource by OC method and the production from OC mining may start declining not in far future. If, thrust on underground mines and increasing production from underground mines is not put as a policy decision, the country may land in a situation when it will not be able to meet the requirement of coal and dependence on import may further increase.

 

Loss of expertise for underground mining is another concern for the country. Underground mining requires special skills for establishing access to the deposit, variety of technologies depending on geo-mining conditions for development and extraction of coal, special skills for supervision and maintenance of safety. Such expertise take time to develop and without a special thrust, it cannot be developed overnight. Declining UG production has led to loss of focus on indigenous manufacturing of equipment for UG production too. Hence, there is a need to pay urgent attention on reviving underground mines and increasing production from underground mines.

 

3.             Major Reasons for Decline in Underground Production

 

To analyse the reasons for decline in underground coal production it would be necessary to examine the geo-technical characteristics of Indian Coalfields, the cost consideration for mining, capability of the technology to yield bulk production to meet the country’s fast-growing demand for coal and the safety of work force. Underground mining in India has not been able to compete with opencast technology on any of these scales and has been given a back sheet by the coal producers. In many coal companies UG mining has been continued to be practiced due to compulsions of retaining the workforce engaged in them. Many of the old UG mines have been converted to opencast both from the conservation aspect as well as for making mining economically viable.

 

3.1          Geo-technical characteristics of Indian coalfields

 

In most of the coalfield seams occur in multiplicity and in close juxtaposition. Some of the seams have multiple splits with partings varying widely. There is wide variation in seam thickness within a small mine take area. Some seams are very thick posing challenges for extraction. Some coal bearing areas like, Noth Karanpura and Rajmahal coalfields in Jharkhand, Talchir and Ib Valley coalfields in Orissa, Moher Basin (Singarauli) in UP and Madhya Pradesh, Korba and Raigarh coalfields in Chhattisgarh have predominantly thick to very thick seams and extensive opencast mining is being practiced there. Other Coalfields like Jharia, Raniganj, Central India Coalfields (CIC) of Chhattisgarh and MP, Wardha and other coalfields of western India and Singareni coalfield of Telangana and the north eastern coalfields in Assam, Arunachal Pradesh and Meghalaya have potentials for mix of technologies of opencast and underground mining.

 

Most of the coal resource lie in thicknesses more than 4m. At places they are banded and are traversed by sills, dykes and intercalations. Faults with varying magnitude of throws and fold are very common in all coalfields. Strata inclinations are generally less than 200 but, in some areas, it varies from 180 to 500. In the north eastern coalfield, it goes up to 800 (1, 1984).

 

Nearly all coals are prone to spontaneous heating. The incubation period varies from 3 to 12 months requiring both fast extraction rate and small panels for extraction. In the past many underground fires have been caused by spontaneous heating leading to diversion of attention of the mine management from production to dealing with fire.

 

The above geo-technical limitations restrict the potential of high production underground mines and affect the economics adversely.

 

3.2          Cost Consideration

 

With the advent of mass production technologies for opencast mining like large capacity Shovels and Dumpers and Surface Miners the cost of production from opencast mines far outweighs that from UG mines. As of now, the cost of production of OC mines, even with a strip ratio of 10 m3/t or more is less than that from UG mines for the same grade of coal and hence makes it more acceptable to the producer on cost consideration.

 

3.3      Surface right availability

 

Availability of surface right for mining has been a major hindrance to maintaining or increasing UG production. As such, seams have been developed on Bord & pillar system and have been left as such, waterlogged due to non-availability of land for depillaring. Around 5 Bt of coal reserves are blocked in pillars today without proper conditions for their extraction. It was opencast mining that enabled extraction of a part of such reserves in shallower depths. However, the deeper developed reserves pose a great challenge today, as these are in stressed physical conditions and waterlogged and have no or less access available for their extraction.

 

3.4      Initial thrust on intermediate technologies

 

Though, mechanisation in underground mines was introduced in a few mines in pre-nationalisation days, like, introduction of cutter loaders, shaker conveyors, chain conveyors, gathering arm loaders, Lee Norse Continuous Miner and Continuous Miners with electric shuttle cars, the pace of introduction did not receive the same priority after nationalization of mines. Coal India tried to introduce Longwall mining in some mines but most of the underground mines practiced Bord & Pillar method of development and partly depillaring with Side Discharge Loaders (SDLs) and Load Haul Dumpers (LHDs). These are low productivity machines and their operation for coal clearance, being a cyclic activity, depended on manual drilling and blasting of coal faces. Manufacturing of such loading machines started within the country and their application became wide spread basically for eliminating manual loading of coal in to mine tubs.

 

3.5      Inadequate infrastructure for handling production potential from mechanisation

 

Most of the mines inherited from the pre-nationalisation days had inadequate transport infrastructure to handle any increase in production from mechanization. In fact in such mines the coal lifter by the SDLs or LHDs had to be transferred in to tubs to be transported out by hope haulages. It was not even sufficient to handle the full capacity of intermediate technology equipment. Mass production technology required completely new construction of matching transport system and surface coal handling system. This required more investment and given the cost consideration compared to opencast mining; such decisions always took a back sheet.

 

3.6      Withdrawal of stowing subsidy for depillaring under built-up areas.

 

Coal Mine (Conservation & Development) Act 1974 was enacted to collect some cess from the coal raised to provide some assistance to the coal producers for some defined activities. One of the defined activities was to give assistance for sand stowing for protective works. This encouraged the coal producers to depillar coal under built-up areas. The practice continued till 2010 or so after which such assistance was stopped and later the Act itself was repealed. This action reduced the production with stowing substantially as the cost of stowing has grown very much with time.

 

3.7      Adverse safety record of underground mines

 

Safety record of UG mines is worse compared to opencast mines. Though, poor safety record of underground mines has not been a tool for reducing the number of such mines, given a choice, one would prefer to reduce the number of accident-prone mines. Poor economics, high safety risks due to waterlogged workings and non-availability of sufficient reserves has led to closure of several underground mines, particularly in BCCL and ECL.

 

4.             Technologies adopted in the past in UG mining

 

India has tried and introduced many underground mining technologies over the years. Bord & Pillar method of Development of coal seams and depillaring has been most predominant. However, several attempts were made to work coal seams with Longwall technology in many mines but this could meet success in only a few mines as stated above.

 

Various technologies tried in different mines can be summarized as follows:

 

Ø  Bord & Pillar

o    Depillaring with caving

o    Multi section depillaring with stowing – several mines with thick seam

o    Wide Stall extraction of pillars with stowing – Bhagatdih, BCCL

o    Knife-edge method with caving – Banki, SECL

o    Partial extraction with leaving stooks – Searsole, ECL

o    Continuous Miner with Shuttle Cars – Initially 3 mines; now at several mines.

Ø  Longwall with individual prop support

o    Single lift with caving – Moonidih, BCCL

o    Multi lift caving with artificial wire mesh roof – Giddi, NCDC

o  Multi section with stowing – thick seams in several mines

Ø  Powered Support Longwall with caving Several mines at different locations

Ø  Powered Support Longwall with sub-level caving and integrated caving in thick seam – East Katras,         BCCL

Ø  Special Methods in specific conditions

o  Multi Slicing with Stowing in steep seams (350) (Jankowice) – Sudamdih, BCCL; Chasnala mine of SAIL

o  Room- Rise (Komora) method with stowing for very steep seam (550) – Sudamdih, BCCL

o  Horizontal Slicing (Kazimierz) in steep seam (300) with stowing.

o  Bhaska Method with caving (700)– Tipong, NEC

o  Drop shield method with caving (700) – Tipong, NEC

 

Introduction of mass production technologies like, Continuous Miner with Shuttle Cars and mechanized Roof Bolters started much later with mixed success. First Continuous miner was introduced in Chirimiri mine of SECL followed by Tandsi in WCL and Jhanjhra in ECL. Initial years saw mixed successes due to poor roof conditions in Tandsi and high cost of the equipment set. With introduction of Continuous Miner Technology, it was proved that given a suitable seam gradient, strata conditions and matching out bye transport system, this technology could boost the underground production. However, this realization came much later when UG production level fell to all time low.

 

Though, individual prop support longwall technology had been practiced in the NCDC’s Giddi and Banki- Surakachhar mines in the pre-nationalisation days, that was the only technology available at that time for introduction in Moonidih mine of BCCL. in early seventies.

 

Powered Support Longwall Technology was first introduced in Moonidih mine of BCCL in 1978, whose application later extended to other mines in the country, like Pathakhera in WCL, Curcha, Kumda, Balrampur & Rajendra mines in SECL, Dhemo Main, Seetalpur, Jhanjhra & Kottadih  mines in ECL, East Katras mine of BCCL and a few mines in SCCL. The technology had to be aborted at most of the mines except, Moonidih, Jhanjhra and GDK7 mine at SCCL, due to various geo-technical issues. Hence, the thrust continued on low productivity SDL and LHD technologies as per the seam gradient suitability.

 

5.             Present Technological Status

 

The status of underground technology has remained same as earlier. The method of work continues to be dominated by Bord & Pillar system. However, there is a shift towards increased deployment of Continuous Miner machines in Bord & Pillar system. CMs have largely replaced LHDs, wherever possible, as the seam gradient condition for application of the two is similar. SDLs continue to be used in steeper gradient seams, where deployment of CMs is not a choice.

 

Longwall technology application has not increased at all, largely due to the properties in existing mines, not amenable for its adoption. As on date also there are three power supported Longwall faces being worked, one each in Moonidih, Jhanjhra and GDK7 mines.

 

Highwall mining has found increased application in some mines and their number is increasing. Though, Highwall Mining is not exactly an underground mining technology, it is considered in UG mining in India, as it is under the ground extraction of coal from surface.

 

As on 31st December 2024, the number of Continuous Miner sets, Longwall sets and Highwall Miner sets in use in Coal India Mines is shown in Table-2.

 

Table-2

Deployment of Continuous Miners, PSLW and Highwall Miners in CIL Mines

(as on 31st December 2024)

 

Name of Company

No. Deployed

Production in FY 2024-25 (Mt)

Productivity range (Avg) (tonne/day)

Continuous Miner

ECL

12

4.599

439 – 1978 (1239)

CCL

1

0.564

1546 (1546)

WCL

3

0.616

885 (885)

SECL

18

7.556

420 – 2313 (1397)

CIL Total

34

13.335

1402

PSLW

BCCL

1

0.463

1269

ECL

1

0.048

539

CIL Total

2

0.512

1125

Highwall Miner

BCCL

1

0.534

1463

ECL

2

0.551

823-1250

SECL

2

0.055

1109

CIL Total

5

1.14

1218

 

There is an increasing trend of deployment of Continuous Miners in CIL mines. Given a suitable working condition, this mass production technology can produce as much as a longwall in India can produce or even more. This is evident from the above Table.

 

6.             Technological options available

 

Having tried various technological options for underground mining over the years in different geological settings it is now established that Intermediate technology cannot meet the increased demand of coal from underground mines.

 

6.1      Powered Support Longwall (PSLW)

 

Longwall technology is mostly not suitable for majority of existing mines, as these have relatively smaller mining lease area and are largely developed on Bord & Pillar system in upper seams. Further, large number of faults in Indian coalfields prohibit application of PSLW, limiting the length and width of panels to be extracted. In many situations the roof behaviour has been unpredictable and quite a few powered supports have been lost due to roof collapses.

 

6.2      Continuous Miner with Shuttle Cars

 

Continuous Miner has succeeded in proving its applicability with mass production in several situations. However, its sustenance requires the surface area to be available for depillaring. Non-availability of surface rights for caving has been a major issue for creation of pillared reserves, so far. To make Continuous Miner technology sustainable in UG mining, it will be essential to acquire surface rights for depillaring with caving so that faster extraction of reserves in mass quantity can be adopted.

 

6.3      Paste-fill technology with Continuous Miner

 

Paste fill technology is an emerging technology under built up areas. Though, this technology has been practiced in metal mines in India too, its application in sedimentary formation is yet to be tried in India. It is believed that this technology is in use in coal mines too, but with high investment. It will be necessary to try this technology in Indian coal mine to establish its techno-economic feasibility.

 

6.4      Highwall Mining

 

Extraction of coal from the periphery of disused/uneconomic opencast mines by Highwall mining technology has been practiced in USA and Australia in several mines. The cost of this equipment, till its production started in India, was very high. In the last 13-14 years, applicability of this technology has increased quite a lot. Study of the existing status of OC mines indicate application of Highwall mining at several sites. Hence, this technology will also have increased potential boosting underground production volumes.

 

It is, therefore, suggested that coal producers should put thrust on large scale application of Continuous Miner, Highwall Miner, Paste-fill technology with Continuous Miner under built up areas and PSLW in geo-technically suitable conditions in greenfield mines. Shortwall mining with powered supports for depillaring pillars developed on Bord & Pillar has also been a success in SECL in the past. This may also be adopted in suitable areas.

 

7.             Coal India Ltd. Plans for Boosting Underground Production

 

For boosting underground production, CIL has made a detailed document named “The Underground Vision Plan of CIL, 2023”.

 

The Vision Plan envisaged boosting underground production to 100 MTPA by 2027-28 (4, 2023) by focusing largely on Continuous Miner and Highwall Miner. The action plan envisages:

 

a.      Scaling up Highwall mines,

b.      Identifying reserves for Punch Longwall mining,

c.      Identifying mines for extraction through Paste-Fill technology,

d.      Working through MDO mode,

e.      Identification and approval of large number of CM/Short wall/Longwall mines,

f.        Planning high capacity UG mines,

g.      Conversion to CM or addition of CM in mines currently using Intermediate technology,

h.      Efficiency enhancement of existing mines/running mines, and

i.        Strengthening of UG wing at Subsidiary and CMPDI.

 

 

7.1          Scheduled and actual deployment of equipment

 

The population of Continuous Miner and Highwall Miner sets to be deployed in different mines is given in Table-3 (4, 2023).

Table-3

Summary of No. of Continuous Miner and Highwall Miners Deployment program in CIL Mines

 

Equipment

Set

Status

2022-23 (Existing)

Population in Operation

2023-24

2024-25

2025-26

2026-27

2027-28

Continuous

Miner

Planned

21

33

55

87

120

142

Actual

21

29

34

Highwall

Miner

Planned

1

3

8

11

11

10

Actual

1

5

5

         


7.3      Envisaged production schedule from different technologies

 

With the above strategies and the action plans made mine-wise, the production plan envisaged vis-vis actual achieved in the last two years are shown in Table-4 (4, 2023).

 

Table-4

Envisaged Production Plan vis-vis actual achieved from UG mines of CIL

(Figures in Mt)

 

Sl. No.

Subsidiary

2021-22

2022-23

Progressive Capacity

(Act)

(Tgt)

2023-24

2024-25

2025-26

2026-27

2027-28

ECL

Planned

12.07

12.93

20.24

25.92

27.81

Actual

9.00

9.85

9.183

8.475

BCCL

Planned

1.50

4.29

7.53

10.08

12.48

Actual

0.810

1.000

0.766

1.139

CCL

Planned

1.59

4.33

6.03

7.53

7.53

Actual

0.760

0.870

0.781

0.706

WCL

Planned

4.32

6.38

8.94

11.99

15.41

Actual

3.040

3.600

2.871

2.776

SECL

Planned

14.53

20.44

26.66

31.41

32.45

Actual

11.530

13.000

11.964

11.868

MCL

Planned

0.44

0.44

0.94

1.44

1.44

Actual

0.500

0.440

0.456

0.479

CIL

Planned

34.45

48.81

70.34

88.87

99.62

Actual

25.626

25.487

26.021

25.442

 

Note – UG production of CIL has remained almost at the same level in the last 4 years, despite increased deployment of Continuous Miners and Highwall Miners largely because the production from other technologies like SDLs and LHDs has reduced.

 

8.             Suggestions for the Way Forward

8.1          Use CM technology, Shortwall and Longwall at suitable locations.

Mass production technologies, like, Continuous Miner and Longwall with powered supports should be used extensively in suitable site conditions. Use of Intermediate Technology in such conditions should be stopped at the earliest. Shortwall with powered support is a proven technology for extraction of developed pillars in Bord & Pillar mines. This should be practiced for faster extraction of pillars. Intermediate technology with SDLs should be practiced in only such areas where application of CM and PSLW is ruled out. SDL technology should be backed with mechnised drilling, roof bolting and coal evacuation. SDL loading into mine tubs should be eliminated.

Availability of land is a pre-requisite for mass production technology. Land acquisition or taking land on lease rent for uninterrupted mass production should be given equal thrust for underground mining as well.

8.2          Extensive R&D studies on strata control required for site specific technology.

Some of the mass production technologies in the past have not given desired results of production and productivity due to roof failures. Extensive R&D studies are required before implementation of such technologies in a particular mine from the point of consideration of strata control. Equipment for roof support should have a matching capacity with the cutting capacity of the face machine.

8.3          Develop technology for cost effective backfilling/stowing/Paste-fill method.

Most of the underground mining reserves underlie built up areas or forests. In both the situations, caving of strata overlying coal seams is not allowed to be done from the considerations of subsidence and possibilities of outbreak of fire in caved goaves. Such areas will necessarily require backfilling, either by sand/bottom ash of power plants or by Paste fill method. It is desirable, therefore, to develop indigenous cost-effective backfilling/stowing technology for its wider application.

8.4          Plan for large size UG mines.

Smaller size underground mines, as is the situation today, do not provide flexibility of movement of working faces. High-capacity underground mines overseas have very large mining lease areas. Some of the high-capacity underground mines have ML area as large as 100 km2. Compared to this the UG mine size in India is very small. This, coupled with the extensive faulting restricts the size of panels to be worked and eventually restricting production capacity of the mine. For planning high-capacity mines the mine size should be at least 10 km2 or more to provide flexibility of operation.

8.5          Scientific studies with numerical modelling must be done before planning for depillaring underneath backfilled OC mines.

Many of the future underground mines are to be planned underneath backfilled areas of opencast mines where top seams have been worked out by OC and lower virgin seams are to be worked by UG method. The OB dumps exert dead weight on the UG mine galleries. Scientific studies with numerical modelling must be done before planning for depillaring underneath backfilled OC mines.

8.6          Develop skills for UG mining with proper training – expertise getting lost.

With gradual reduction of UG mines the manpower having received appropriate training in UG mining have either retired or have been diverted in OC mining. UG mining needs specialized skills and managerial capabilities. It is, therefore, necessary to train and retrain the required manpower in UG mining of proposed technologies. In the past many executives had been given exposure to good UG mines of different continents. Such trained persons had delivered well. The same practice should be adopted at this also, when the country is looking for setting up high capacity UG mines. 

8.7          Faster sinking of Shafts and drivage of Inclines is essential.

Deeper UG reserves require access through shafts or inclines. Sinking of shafts and drivage of inclines are specialized jobs for which special skills are required. In the late seventies and early eighties a few new shafts were sunk in the coal sector for which help of foreign experts were taken. The industry has lost such expertise gained through such assistance. Domestic companies need to be set up for taking up such jobs for faster shaft sinking and incline drivage. CIL and SCCL, with their large experience of UG mining, should set up wings for UG mine construction and provide expertise to the new UG coal mining player.

9.             Policy Initiatives Required by Government of India

Production from underground mines cannot pick up until the Government of India takes up some policy initiatives. So far, it has been left up to the production companies, which take the path of least cost production. While economically it may be justifiable, for the long-term sustenance of domestic production matching with the demand projection, it is essential now for the Government to come forward and take some policy decisions to facilitate increased production from underground mines. Some of the suggested policy initiatives are as follows:

9.1          Facilitate domestic production of underground mining equipment.

With decline in underground mine production, the manufacturing capacity of equipment for underground mining has also gradually reduced in the country. Domestic UG coal producers, today, have to depend on imports for procurement of equipment for UG mining, which are both costlier as well as suffer for spares availability. Government of India should direct one of its mining equipment manufacturing companies, say BEML, to collaborate with overseas manufacturers and start producing all sorts of equipment viz, transport, coal extraction, man riding, material transport, vertical transport, main mechanical ventilator etc. for domestic UG mining.  

9.2          Allocate underground mines of size more than 10km2

The mine size allocated should be large enough for selecting alternative mining areas in case of problems in one area. This is more so required as Indian coalfields are infested with large scale faulting. Internationally, high capacity UG mines are of very large areas, some as high as 30-40km2. Though, this may not be possible in this country, as the coalfields have multiple seams, it is suggested that the minimum size of coal block allocated for UG mining should be 10km2.

9.3          Enter into bilateral Agreements with countries advanced in underground mining

In the period just after nationalization of coal industry, several bilateral agreements were interred into with various advanced countries in UG mining at that time, which led to development of a few UG mines including the present day Jhanjhra and Moonidih mines. Government policy of withdrawing bilateral agreement concept and leaving it open to competitive participation has pushed UG mining towards back door. As of today, advanced UG mining countries are China, Australia, Poland, Czech Republic and USA only. Government of India should have mine specific bilateral agreements with these countries for developing high capacity domestic UG mines.

9.4          Restore Coal Mine (Conservation & Development) Act 1974

Coal Mines (Conservation and Development) Act 1974 was brought in to help improve extraction of coal under built up areas apart from other activities for development of coal belts. This had helped the coal producers in depillaring under built up areas as subsidies were available for sand stowing. With the abolition of this act depillaring with hydraulic sand stowing has become highly uneconomic, compelling the coal mining companies to resort to only development of coal seams under built up areas and leaving them at that stage. Such areas become inaccessible later due to spalling of roof and sides and the reserves get sterilized for ever for mining, unless extracted by OC mining. It is therefore suggested that the above Act should be restored to facilitate complete extraction of coal under built areas and forests and subsidies may be provided to the coal producers. For this CCDA Cess, as levied earlier may be re-imposed.

9.5          Facilitate creation of mine construction companies for mine development

Development of a new underground mine requires a lot of construction works like shaft sinking, incline drivage, in seam drift drivage etc. These are one time works and require a lot of specialized skills. Some skills were developed in the past with collaboration with advanced countries like Poland and Russia. These are lost now as most of the trained people have retired. It is necessary for Coal India particularly, to create a subsidiary for mine development which could provide specialized services to the domestic mine developers for creating these facilities. It may not be possible for individual mine owners to create such facilities.

Government of India should direct Coal India Ltd to create one such subsidiary and develop the necessary expertise required with required equipment. The Business Development Directorate of Coal India should be given this task to create such a company.

9.6          Create R&D fund for increased research in underground mining technologies

Research and Development in underground mining technology needs further push by infusion of more capital as well as involvement of research organization. Research organisations like, CIMFR, CPMDI, IITs and other institutions having research facilities in mining, should be given specific funds and tasks to develop best high production mining technologies for specific mines/areas. Government of India should create a large pool of fund by levying R&D cess on coal production for this purpose.

9.7          Create stricter norms for land & environmental degradation by opencast mines with heavy taxation

In the present system of approval of OC mines, the costs of land and environmental degradation are not factored adequately. The present laws do not compel mine owners to return the land restored to its original or near original topography. While the underground mines do not disturb the land and environment to the extent OC mining does, it must compete with OC mine production cost to be economically viable. To create a level playing field for both the technologies, it should be made mandatory for both the technologies to adhere to the same standards in land and environmental restoration. This will most likely make UG mining a choice on cost consideration.

9.8          Facilitate development of cost-effective Paste-fill technology

Paste-fill technology is a recently developed technology for mining under areas to be protected on surface without subsidence. While this technology has been largely practiced in metal mines, its application in coal mines has been limited to some mines in China. It is learnt that China is doing it successfully in some mines but its cost is high. The capital cost required for the specialised equipment for this technology is very high. Adoption of this technology, if found economically viable, would open large prospects of mining under built up and forest areas without causing any subsidence.

Government of India should inter in to a bilateral agreement with Government of China for taking up a pilot mine for this technology with the condition of technology transfer. Coal India may be directed to identify one such mine for the purpose to introduce this technology.  

10.          Conclusions

 

Gradual reduction in the number and production of underground mines has compelled people and the government to make plans for its reversal. Major reason for such decline has been the competitive cost of production of coal from opencast mining and largescale development of equipment manufacturing capacity domestically for OC mining. Some of the deeper OC mines have their own problems of high strip ratio, cost, and slope stability. This has compelled us to think of increasing production from UG mining. Though, UG mining cannot meet the total requirement of coal despite the best efforts, it is imperative for all stakeholders to reverse the declining trend and boost UG production. Mass production technology must be adopted extensively with matching mechanization in all sub-systems. Acquisition of surface rights for mining, creation of domestic expertise in UG mining, manufacturing of UG mining equipment indigenously etc. would be necessary for reversal of this trend. CIL has made a vision plan for increasing UG production to the level of 100 MTPA by 2027-28. However, in view of the experience, its implementation is a great challenge. It needs to be implemented with strict monitoring at the highest levels.

 

It is also mandatory on the part of the Government of India to take some policy initiatives to facilitate increased production form underground mines. Some suggestions have been made in this paper. 


 

----------------------------------------------------------------------------------------------------------------------

References:

1.    Coal Mining in India – A CEMPDIL publication, 1984.

2.    Coal Statistics 2013-14 – A Publication of Coal Controller of India, 2014

3.    Coal Statistics 2023-24 – A Publication of Coal Controller of India, 2024

4.    The Underground Vision Plan of CIL, 2023.